Azure Uptime Report: OakLeaf Table Test Harness for April 2010 (99.71%)

Following is the Pingdom monthly report for a single instance of the OakLeaf Systems Windows Azure Table Test Harness running in Microsoft’s South Central US (San Antonio) data center:

image 

The April 2010 downtime data is similar to that for previous three months of Azure’s commercial operation, which began on January 4, 2010.

Note that the OakLeaf application is not subject to Microsoft’s 99.9% availability Service Level Agreement (SLA), which requires two running instances.

It’s not known how many, if any, of the 6 outages were planned for, as an example, fabric operating system upgrades.